Close Menu
  • Home
  • Latest News
  • Top stories
  • Local News
  • Politics
  • Business
  • Entertainment
  • More
    • Sports
    • Nollywood
    • Tech
    • Editorial
    • Health
    • World
    • Lifestyle
  • Africa
    • Kenya
    • Nigeria
    • South Africa
Sports

“How i secured US$15M Glo sponsorship”-Kwesi Nyantakyi provides principles for sponsorship

August 26, 2026

CAF CC: CAF names Kasongo to handle Nations FC vs. FC Diarra tie

August 25, 2026

Asante Kotoko announce resigning of former captain Boadu on a two-year deal

August 25, 2026
Facebook X (Twitter) Instagram
Ghanamma.comGhanamma.com
  • Home
  • Latest News

    Dolly Parton, country music icon, dies after brief battle with cancer – updates

    August 26, 2026

    South Africa’s space programme needs one learner to make space history

    August 26, 2026

    Kenya’s biggest stadium project since 1987 takes shape for AFCON

    August 26, 2026

    Nigerian film star Ogogo dies from cancer aged 66

    August 26, 2026

    Truck crash halts traffic on Lagos-Ibadan Expressway

    August 26, 2026
  • Top stories
  • Local News
  • Politics
  • Business
  • Entertainment
  • More
    • Sports
    • Nollywood
    • Tech
    • Editorial
    • Health
    • World
    • Lifestyle
  • Africa
    • Kenya
    • Nigeria
    • South Africa
Facebook X (Twitter) Instagram Pinterest Vimeo
Subscribe
Ghanamma.comGhanamma.com
Home»Top stories»Afari Hospital: Only $500,000 outstanding, not $85m – Minority
Top stories

Afari Hospital: Only $500,000 outstanding, not $85m – Minority

Ghana NewsBy Ghana NewsJune 17, 2026No Comments3 Mins Read
Facebook Twitter Pinterest LinkedIn Tumblr Email
Share
Facebook Twitter LinkedIn Pinterest Email Copy Link

The New Patriotic Party (NPP) Minority Caucus in Parliament has denied claims by the government that a total of US$85 million remained outstanding to the contractor working on the Afari Military Hospital in the Ashanti Region.

According to the caucus, the outstanding amount owed the contractor working on the project was US$ 500,000, and not US$85million as stated by the government.

Addressing a press conference in Parliament yesterday, the Deputy Ranking member on Parliament’s Defence and Interior Committee, Mr Kofi Amankwa-Manu, said records of both the Ministries of Finance and Defence did not support the claim.

He explained that the overall completion rate of the project as of January last year stood at 98 per cent.

“The narrative being peddled that the 500-bed facility is only 60 per cent complete, is a complete fabrication designed to justify an outrageous financial demand. Official records from the Project Implementation Unit of which I was the Chair of the Ministry of Defence confirm that as of September 2024, the core hospital was 92.5 per cent complete,” he said.

“By January 2025, under the previous administration of the NPP, the overall completion rate stood at an impressive 98 per cent,” he added.

Providing a breakdown of the completion rate of the project, Mr Amankwa-Manu stated that civil works and core hospital, architectural works, support facilities and staff housing, roads, and landscaping works, were 97.5 per cent, 87 per cent, 77 per cent, 80 per cent and 77 per cent complete as of September 2024.

Furthermore, he noted that both the original contract term of US$180 million and the negotiated additional funding of US$19.3 million due to the delay of the completion of the project had been paid.

“Out of a subsequent US$3 million claim negotiated from over US$ 6.5 million, US$ 2.5 million has been paid. To jump from an outstanding balance of US$ 500,000 to a sudden demand for US$ 85 million is not just mathematical, it is indeed criminal,” Mr Amankwa-Manu added.

He alleged that the relocation of the project by the NDC government caused its delay for six years and resulted in the contractor claiming an additional US$36 million, which was eventually negotiated down to US$19.3 million.

Mr Amankwa-Manu called on the government to ensure that the remaining two per cent of the project was completed to serve its intended purpose.

It would be recalled that security personnel at the hospital recently turned away the Ranking Member of Parliament’s Health Committee, Dr Nana Ayew Afriyie and a delegation of Ashanti Region MPs during a visit to the project site.

During the stand-off, the MPs argued that they were there to assess progress on the project, but the soldiers maintained that entry into restricted areas required clearance.
 

BY BENJAMIN ARCTON-TETTEY

Follow our WhatsApp Channel now! 

Share. Facebook Twitter Pinterest LinkedIn Tumblr Email
Ghana News
  • Website

Related Posts

Dolly Parton, country music icon, dies after brief battle with cancer – updates

August 26, 2026

Nigerian film star Ogogo dies from cancer aged 66

August 26, 2026

World’s largest hospital ship begins free surgery for 4,745 Ghanaians

August 26, 2026
Leave A Reply Cancel Reply

You must be logged in to post a comment.

Top Posts

Ghana Power Utility Deploys Infrared Technology to Prevent Grid Failures

August 25, 20260 Views

Seafarer assessment systems must evolve with maritime technology – IMO official

August 24, 20260 Views

Digital tech key to boosting Ghana’s agribusiness  – Experts

July 12, 20260 Views

Ghana Launches Revolutionary E-Visa System to Revolutionize African Travel and Trade Through Digital Innovation

July 11, 20260 Views

Ghana Launches Groundbreaking E-Visa System to Revolutionize African Travel, Trade, and Mobility

July 11, 20261 Views
About Us
About Us

Ghanamma is an independent digital news platform delivering timely updates and reliable information across politics, business, technology, health, entertainment, sports, and world affairs, helping readers stay informed through trustworthy journalism and meaningful insights.

Facebook X (Twitter) Pinterest YouTube WhatsApp
World News

South Sudan’s leader sacks aides after dead man appointed

February 4, 2026

South African white separatists claim land acquired from Zulu king then lost to British

February 2, 2026

Muhoozi’s outbursts expose Uganda’s unease with funding Somalia war

February 2, 2026
Top stories

University of Ghana Attributes Fee Increases to Student Leadership Charges

January 2, 20262 Views

Sam Jonah, 3 Others Cleared Of Criminal Charges In River Park Estate Dispute In Nigeria

January 2, 20262 Views

GCNH donates health logistics to Ho Municipal Health Directorate  

January 2, 20261 Views
  • About Us
  • Contact Us
  • Cookies Policy
  • Privacy Policy
  • Terms & Conditions
  • Disclaimer
© 2026 Ghanamma. Designed by Ghanamma.

Type above and press Enter to search. Press Esc to cancel.