Source: The Conversation Africa
But getting the players in the energy space to do that is proving to be difficult. Around 74% of the country’s electricity is generated by coal-fired power stations owned by the state-owned electricity provider, Eskom. This makes
Read more:
Reforms are underway to unbundle Eskom and introduce more competition. But for years, it has operated as a near-monopoly, with coal at its centre.
A recent court case illustrates how difficult it is to break Eskom’s monopoly, even for huge corporations that want to switch to solar.
In 2023,
This would have freed up electricity for homes, hospitals, schools and other businesses to use and would have reduced the amount of greenhouse gas emissions being pumped into the atmosphere.
Read more:
But the mine’s plan met strong resistance from the state utility. For over a year, Eskom refused to allow the mine’s solar power lines to cross its servitude (run cables across the same land that Eskom’s power lines run across). Eskom had granted all other approvals for the project had been granted.
The mining company took the case to court. It argued that Eskom’s refusal was unlawful, based on errors of law and improper motives, and that Eskom hadn’t proved there would be technical or safety problems if the solar power lines crossed the servitude.
In
Read more:
I am a specialist in environmental and climate change law who researches how international and domestic law can be used to advance climate justice in
The court ruled that Eskom cannot use red tape to block renewable energy projects that follow the law. This gives energy investors more certainty. But it also exposes how resistance to solar energy from powerful institutions like Eskom can slow
How Eskom tried to derail the solar project
Sibanye mine’s planned solar facility was designed as a “behind-the-meter” project. This means it would generate electricity mainly for its own use rather than to sell back to the national grid.
To connect the solar plant to its own electricity substation, the company needed Eskom’s wayleave (administrative permission to build within Eskom’s infrastructure corridor) to build a 6km power line crossing Eskom’s servitude. (Anyone who wants to run cables, pipelines or other infrastructure across land where Eskom’s power lines are located must obtain this permission, to ensure safety and protect the network.)
Read more: Should governments pay businesses for climate disasters? Researchers unpack huge lawsuits in
The mine’s planned solar facility had already secured all necessary regulatory approvals from government and had complied with technical and grid code requirements. It was also designated as a
Eskom’s internal technical units supported the project, on condition that the mine would use underground cables in the area where it crossed Eskom’s infrastructure, for safety reasons. Eskom then asked for and received payment of R15 million (
Read more: Corruption and clean energy in
But Eskom’s ad hoc distribution executive committee later rejected the permission. It claimed the project posed regulatory and operational risks. Instead, the utility proposed that the solar plant connect at a different substation and that the electricity be transported through Eskom’s network to the mine – a process known as “wheeling” – at an additional charge of about 30%. The mine told the court that this extra cost would have made the project too expensive to proceed.
Why the court intervened
Eskom, which depends heavily on selling electricity to large industrial customers, faces declining revenue as more companies generate their own renewable power. The scale of this shift is significant. Since 2018, the National Energy Regulator of
But under
The court reviewed Eskom’s refusal to grant the wayleave under the Promotion of Administrative Justice Act, which gives effect to the constitutional right to lawful and reasonable administrative action. It found that Eskom’s decision was unlawful and invalid. It held that the project did not pose risks and that Eskom had acted for an improper purpose, namely to protect its revenue.
Read more:
The court also rejected Eskom’s claim that it had a “right of first refusal” under the Electricity Regulation Act.
The court took the unusual step of ordering that the wayleave be granted. This is an extraordinary step in administrative law, reserved for exceptional circumstances. (Ordinarily, the court would have sent the matter back to Eskom to reconsider.)
Why the case matters
This case is not just about one mine.
When large industrial users like mines generate their own renewable power, they:
- reduce pressure on the national grid
- potentially free up electricity for other users
- reduce greenhouse gas emissions and prevent further global warming
- bring private capital into the energy sector
- create and protect jobs.
Read more: Nuclear and coal lobbies threaten to scupper renewables in
These are all elements of a just energy transition, a shift to cleaner energy that also supports economic stability and livelihoods.
When lawful renewable projects aligned with national policy are blocked for commercial reasons, investment slows down. Uncertainty grows and confidence in legal reform weakens. The consequences reach beyond one company’s profits. They may influence how quickly
Policy ambition versus institutional practice
The judgment also exposes structural tensions within
Read more:
This tension is not unique to
The High Court’s decision signals that the rule of law remains central to
Copyright 2026 The Conversation Africa. All rights reserved. Distributed by AllAfrica Global Media (allAfrica.com)., source