Ghana’s planned 2,000MW nuclear plant could cost up to $30bn – ACEP
Ghana’s planned 2,000-megawatt nuclear power plant could cost between $15 billion and $30 billion, according to the Africa Centre for Energy Policy (ACEP), raising questions about the project’s financing and potential long-term implications for public finances.
In its analysis of the 2027 Budget Statement, the energy policy think tank warns that the scale of investment required could expose the country to significant financial liabilities, particularly if government proceeds without a clearly defined financing plan.
ACEP estimates the cost based on international nuclear projects, including large reactor developments in Egypt and the United States, which have recorded substantial investment requirements.
The estimates draw on comparable projects, including Egypt’s El Dabaa nuclear plant, where a Russian state loan covered 85% of construction costs and is repayable over 22 years at an interest rate of 3%.
ACEP says the financing arrangement illustrates the potential sovereign liabilities associated with vendor-backed nuclear projects, particularly where government assumes responsibility for funding.
The concerns come as government plans to commit $200 million to a 24-month nuclear readiness programme from January 2027 to December 2028. The programme is expected to culminate in the signing of an engineering, procurement, construction and financing contract by the end of 2028.
However, ACEP says the 2027 Budget does not outline an annual disbursement schedule for the readiness programme or provide details of the financing terms expected from international partners, despite government’s plan to fully own the plant.
The think tank is also questioning the competitiveness of the vendor selection process following Ghana’s agreement with Russia, after earlier framework agreements with vendors from the United States and China.
It says meeting the December 2028 target will depend on key legal and technical milestones, including the passage of the Nuclear Power Corporation Bill and the completion of site acquisition and characterization.
ACEP is therefore urging government to clarify how the financing, procurement and legal processes will be sequenced to ensure the project is financially sustainable and can meet its proposed timelines.