Ahmed Ibrahim: GARID flood-control projects awaiting Finance Ministry clearance
The Minister of Works, Housing and Water Resources, Ahmed Ibrahim, has revealed that six flood-control projects under the Greater Accra Resilient and Integrated Development (GARID) Project are awaiting financial authorisation from the Ministry of Finance before construction can begin.
The projects, which are aimed at strengthening Accra’s resilience to flooding and climate-related risks, are currently at the tendering and contract award stage.
Mr Ibrahim disclosed this on the floor of Parliament on Wednesday, November 18, 2026, while responding to questions on the government’s efforts to address perennial flooding in the capital.
The projects include the reconstruction of the Abbosey Okai Bridge, construction of the Atomic East and West detention ponds, improvement works on the Alajo drain, repackaging of works on the Nima drain, and installation of the Accra Flood Early Warning Systems.
He explained that the commencement of the projects depended on the Ministry of Finance granting the required commitment authorisation to enable contracts to be awarded and construction works to begin.
On the Nima-Paloma drainage project, Mr Ibrahim said the previous contract had been terminated and the project would be repackaged and re-awarded to a new contractor after the necessary financial commitment had been secured.
At the time of termination, progress stood at 13 per cent for evacuation of works, 25 per cent for demolition of the existing drain, 9.7 per cent for casting of the concrete base and 9.5 per cent for casting of concrete walls.
He said the Ministry had engaged Dredge Masters to desilt the Nima-Paloma drain to improve stormwater flow while efforts were being made to secure financial clearance for the project’s continuation.
Mr Ibrahim added that additional local measures had been introduced to reduce the exposure of communities along the upstream and downstream sections of the Nima drain to flooding.
The Ministry is also engaging relevant stakeholders, including the World Bank, to determine the appropriate procurement arrangement for appointing a new contractor to complete the project.