World Bank Raises Concern Over KSh1.2 Billion Monthly Losses on Stalled Isiolo-Mandera Road
The World Bank has warned the Kenyan government that delays in compensating landowners affected by the construction of the Isiolo-Mandera Highway are exposing the KSh168 billion project to billions of shillings in additional costs.
In a letter addressed to Treasury Cabinet Secretary John Mbadi, Roads and Transport CS Davis Chirchir and Lands CS Alice Wahome, the bank’s Kenya Division Director, Qimiao Fan, raised concerns over the slow compensation process, which has prevented contractors from accessing some sections of the 740-kilometre highway.
Fan cautioned that continued delays could disrupt construction schedules, increase contractual risks and push the project’s overall expenditure beyond the allocated budget.
According to the World Bank, each additional month of restricted access to construction sites exposes the project to approximately KSh1.2 billion in extra expenses.
The amount comprises about KSh1 billion in recurring costs, including security, supervision, idle equipment, personnel and site facilities, alongside approximately KSh207.5 million required for equipment demobilisation and remobilisation.
The bank further questioned why compensation had taken so long despite funding being available since 2024.
It revealed that the process only started in November 2025 and had initially been restricted to the Isiolo-Modogashe section.
Out of 1,669 people affected by the project, only 1,281 had received compensation by the time of the assessment.
On the Isiolo-Kulamawe section, the government had paid KSh456 million, while continued delays were exposing the project to an estimated KSh536 million in additional monthly costs.
The Wajir-Tarbaj-Kotulo section was facing a similar challenge, with the bank estimating monthly financial exposure at KSh421 million. The Kotulo-Kobo-Eluaki section was also recording delays, with potential additional costs of KSh243 million every month.
The highway is being constructed under the World Bank-funded Horn of Africa Gateway Development Project, which is intended to improve transport connectivity in northern Kenya.
As of October 26, 2026, construction had reached 60 per cent completion. The project was initially expected to be completed in January 2028, but the deadline has since been pushed to around 2030.
https://www.kenyans.co.ke/news/129405-world-bank-raises-alarm-over-delayed-compensation-ksh168-billion-isiolo-mandera-road
NAITIRI_MEDIA feedback-opera-news-app@opera.com
Reported by News Hub Creator.
Read Original Report at news hub creator ↗
Comments (0)
No comments yet. Be the first to share your opinion!