Listen to this article Share Nigeria’s ageing Apapa and Tin Can Island ports face declining cargo volumes and slower vessel turnaround, as an eight-month delay to the N1.3 trillion reconstruction prolongs inefficiencies at the country’s busiest maritime gateways.
Together, the two ports handle more than 85 percent of Nigeria’s trade, according to the National Bureau of Statistics (NBS). But deteriorating infrastructure and longer vessel turnaround times are weakening their competitiveness against better-equipped regional ports.
Commissioned in 1926, Apapa port is nearly a century old, while Tin Can Island port began operations in 1977.
Both remain critical to Nigeria’s maritime trade, largely because of their proximity to the country’s commercial centre, despite years of inadequate infrastructure investment.
Data from the Nigerian Ports Authority (NPA) shows that Apapa’s cargo throughput fell five percent to 535,000 tonnes in the six months to June, while container traffic also declined.
Inward cargo, which accounts for the bulk of the port’s traffic, dropped 5.3 percent, while 18 fewer vessels called at the port compared with the corresponding period of 2025.
Vessel turnaround time, the period between a ship’s arrival and departure, increased from 5.9 days to 6.1 days, while berth occupancy rose from 47.7 percent to 49.3 percent, indicating that vessels occupied berthing facilities for a larger share of available time.
At Tin Can Island, overall cargo throughput recorded modest growth, but operational indicators also pointed to mounting pressure.
Vessel calls fell 3.4 percent to 488 from 505 in the first half of 2025, while turnaround time increased from 4.4 days to 5.1 days.
Berth occupancy rose from 40.2 percent to 45.7 percent, while a 19.9 percent decline in outward cargo partially offset growth in inward shipments.
Beyond vessel movement, the time cargo spends in Nigerian ports before clearance also highlights the scale of the efficiency problem.
The Nigerian Shippers’ Council’s 2024 annual report put average cargo dwell time at 13 days, marginally lower than the 14.1 days recorded in 2011, representing an improvement of just over one day in 13 years.
According to the Sea Empowerment and Research Centre, a maritime think tank, average cargo dwell time in Nigerian ports remained between 10 and 18 days in 2026, compared with seven to 10 days in Lomé and Tema. This remains significantly above the global best practice of three to five days.
Prolonged cargo dwell times increase the cost of moving goods through Nigerian ports, exposing importers and exporters to higher storage, demurrage and logistics expenses while making supply chains less predictable.
Emeka Akabogu, a maritime lawyer, said Nigeria must significantly reduce cargo dwell time to improve port efficiency and support its ambition of building a $1 trillion economy by 2030.
“If we want to achieve $1 trillion, we might put it at about 5.3 to 7.5 million containers per annum,” he said.
The operational difficulties also weaken Nigeria’s ability to compete for regional maritime traffic as shipping lines increasingly favour ports with deeper berths, modern cargo-handling equipment and faster vessel turnaround times.
Nigerian ports have been absent from Lloyd’s List One Hundred Ports ranking for ten consecutive years, while regional competitors including Tanger Med in Morocco, Port Said and Alexandria in Egypt, Durban in South Africa and Lomé in Togo continue to feature.
Industry stakeholders have identified the infrastructure deficit as a major reason for Nigeria’s exclusion.
The NPA reported container throughput of 2.1 million twenty-foot equivalent units (TEUs) across the country’s seaports in 2025. Tanger Med, the highest-ranked African port in the 2026 ranking, handled about 11.1 million TEUs in the same period.
“Vessels do not come to ports that are not automated and advanced,” Temisan Omatseye, a former director-general of the Nigerian Maritime Administration and Safety Agency, told BusinessDay in an earlier interview.
“They are not happy coming to Nigeria because the turnaround time is too long. A vessel sitting at the quayside is losing money. They want to keep moving. Think of a port that does 48-hour turnaround time; by the time Nigeria is done with one turnaround after six to seven days, they have done three rounds elsewhere,” he said.
Beyond slowing vessel movement and cargo clearance, obsolete port infrastructure is increasing operating costs for businesses, with importers bearing much of the financial burden through higher logistics charges, delays and demurrage.
Shallow channels force larger vessels to wait for high tide or offload cargo onto smaller feeder ships, adding to shipping costs. Weak quay aprons also limit terminals’ ability to deploy heavy, modern cranes, extending vessel turnaround times and increasing the risk of demurrage charges.
The financial consequences are significant. The Nigerian Ports Authority (NPA) has reported that Nigeria loses more than N1 trillion annually due to inadequate port automation and modern infrastructure.
The proposed modernisation programme is expected to address some of these constraints through the upgrading of quay walls, deepening of channels, replacement of cargo-handling equipment and expansion of terminal capacity to accommodate larger vessels and growing trade volumes.
However, the cost of inefficiency is already being passed on to businesses.
Boma Alabi, chairman of the Shipping Association of Nigeria, said earlier this year that logistics and clearance costs in Nigeria were roughly 30 percent higher than those of regional peers in West Africa.
In some cases, congestion and procedural delays alone add between 20 and 30 percent to the final landed cost of imported goods.
The problem is not limited to vessels waiting to berth. Obsolete cargo-handling equipment within terminals also slows the movement of containers from ships to storage yards, creating further delays for importers and truck operators.
Sulaiman Ayokunle, spokesperson for the Association of Nigerian Licensed Customs Agents (ANLCA), said containers discharged from vessels often cannot be moved efficiently from the quayside to the main storage yard because of inadequate handling equipment.
BusinessDay observed that some cargo-handling equipment at Apapa port was obsolete, limiting the speed at which containers could be transferred and increasing waiting times for trucks.
Even where machinery is available, its age and technological limitations undermine operational efficiency.
“Port and terminal management is capital intensive. Heavy duty consignment requires heavy duty handling machines. So if what you have is obsolete presently, you have congestion even from the seaside, because the equipment to move some of this container to the main yard are obsolete. The ones we call new, some other countries have already gone past that,” Ayokunle said.
These delays have direct financial implications for importers, particularly through demurrage charges incurred when containers remain at ports beyond the free storage period.
Ayokunle said shipping lines typically offer importers three free days to clear their containers, but delays at the ports can keep consignments there for as long as 13 days.
He illustrated the financial burden with an importer handling 10 containers. At an estimated demurrage charge of N63,000 per container daily, keeping the containers for 10 additional days would result in N630,000 per container, or N6.3 million across the shipment.
The delays also affect truck operators, who sometimes wait for extended periods to load containers because the necessary handling machinery is unavailable or inefficient.
“When you position your truck for loading, sometimes they will tell you, you might be there for 24 hours. Why? Because the machines to take care of these loadings are not readily available. When they are available, they are obsolete,” he added.
The financial burden on businesses persists as the Federal Government struggles to commence the N1.3 trillion (£746 million/N 1,791.44) rehabilitation of Apapa and Tin Can Island ports, a project expected to address some of the infrastructure deficiencies driving up cargo-handling costs and vessel turnaround times.
Eight months after Nigeria signed a financing agreement with the United Kingdom during President Bola Tinubu’s visit in March, physical reconstruction has yet to begin, despite the government missing two previously announced construction deadlines.
The project is designed to rehabilitate deteriorating quay walls and berth infrastructure at both ports, replace paved areas and install new fenders and mooring structures.
The scope of work extends beyond quay walls and berths. Construction documents by ITB Nigeria, the contractor engaged for the works and obtained by BusinessDay, also detail plans to rehabilitate bollards, safety ladders and apron slabs, alongside structural works to support modern ship-to-shore gantry cranes at Tin Can Island port.
The documents put the project cost at $901.86 million.
The rehabilitation is expected to improve berthing and cargo-handling capacity, reduce vessel turnaround and cargo dwell times, and lower demurrage and logistics costs for importers and exporters.
It could also make Nigerian ports more attractive to shipping lines seeking efficient routes into West Africa, according to officials at the Nigerian Ports Authority who spoke to the Nigeria Ports Consultative Council in September.
In April, Bolaji Akinola, special adviser to Adegboyega Oyetola, the minister of Marine and Blue Economy, said construction would begin in the second quarter of 2026.
By July, Abubakar Dantsoho, managing director of the Nigerian Ports Authority, said preliminary investigations, including borehole drilling, had been completed and contractors were expected to mobilise to the site in the third quarter. Neither deadline was met.
Dantsoho had previously put the construction period at 48 months. The delay in mobilisation could therefore push completion beyond the anticipated late-2030 timeline.
The financing agreement includes substantial procurement commitments to British companies. At least £236 million in supplier contracts is expected to go to UK firms, including a £70 million contract for British Steel to supply 120,000 tonnes of steel billets for the reconstruction.
The British Steel order is the company’s largest export contract backed by UK Export Finance.
However, the Federal Government is still expected to fulfil its counterpart funding commitments before the project can fully move into its construction phase, according to a source within the NPA.
The source told BusinessDay that the first phase had received Federal Executive Council approval for disbursement by the Central Bank of Nigeria and that mobilisation to the site was expected in November.
The source did not disclose the amount of counterpart funding required or whether the approved funds had been released.
BusinessDay’s enquiries to the NPA’s communications office on the funding arrangements and revised construction timetable were unanswered as of press time.
Akinola told BusinessDay that preparatory work had started and that the project remained on course.
“You will hear a major development in two weeks,” he said.
Bethel Olujobi is the Trade Correspondent at BusinessDay. He brings scarce insight into Nigeria’s maritime policies and the changing currents of global commerce defining the country’s position in international trade. Before this, he reported on foreign relations, migration and sports for BusinessDay. He holds a Bachelor’s degree in Mass Communication, and is an alumni of the CNN Academy and the Financial Times News School. He is certified by Reuters and Google. He is based in Lagos, Nigeria. For pitches, email: betheljobi@gmail.com