Public Works Minister Samuel Kofi Woods Tuesday morning inspected ongoing rehabilitation work at the Executive Pavilion in central Monrovia and expressed dissatisfaction over the progress of work, but took responsibility as infrastructure minister.
“I must be honest I am not very happy. I am not happy about the progress,” Minister Woods who held lengthy discussions with officials of the contractor, Afrique Maintenance and Construction Company (ACMC), said.
He said the slow pace is from all sides, but from the Ministry in particular because its technicians were not proactive. “The Ministry of Public Works technicians need to be proactive, they have to be more aggressive on the field, and I think on this one I don’t see that level of aggression and pro-activeness that is required,” admitted the Minister.
He said he would meet with the company and the Ministry’s technical team Thursday to find a conducive and speedy way forward-to come out with a work plan that is clear and definite.
The Minister said his unhappiness stems from issues that has to do with the Ministry itself “and that is why we believe the Ministry should address some of these issues.
Minister Woods said there were number of reasons given by the contractors that were unforeseen including changing the original roofing to POP instead. He said the use of the new design takes time and is associated with additional costing to the overall cost of renovating the pavilion.
About US$100,000 more is needed to handle the situation. “And that requires proper approval because it will be affecting our budget and the commitment made on it financially. That is why it has been delayed.”
The aspect of budgeting, he said, is beyond the Ministry of Public Works and will involve the Ministry of Finance.
“But in addition to that, I think the decision making process from the Ministry of Public Works sides, from our technicians side, I think is slow.”
The Infrastructure boss said the Executive Pavilion and the Belleh Yellah road projects are the two that have come under red-light at the Ministry of Public Works, “what we call urgent emergency situation.”
He took the responsibility and stated that “We have to be men. Men must be courageous to identify success, challenges and we must assume responsibility when there are problems.”
The Public Works Ministry recently instituted legal action against several construction companies for defaulting on contracts signed with the Ministry.
The Ministry argues that these companies had not lived up to the letters of the agreements and must pay back monies disbursed to them, but several of the companies listed litany of constraints including solicitation of bribes by some officials of the Ministry.
They did not and have so far failed to name said official despite a challenge thrown at them by the Minister.
Many individuals in the public have also criticized Afrique Maintenance and Construction of doing little or no work since it began reconstruction the Pavilion for over year now.
Some have called on the Ministry to rearward the contract to another competent company, but Minister Woods has now laid the matter to rest.
“I take responsibility, I assume responsibility to work and correct them, and I think the Ministry needs to be very proactive.”
Minister Woods said he will pressure technicians of the Ministry, especially those associated to the Pavilion, to be proactive in meeting the ministry and government’s deliverables.
“They must be proactive and know that it is government’s work that needs to be completed. I will not shift responsibility on anybody else, but we have the responsibility to perform and as Minister and my responsibility is to make our people at public works perform.”
However, Minister Woods said like the new health Ministry which completion has a definite time of October 2011, a definite completion time will be given the Pavilion after Thursday’s meeting.
Meanwhile ACMC Project Manager Alieu V. Kermokai told this paper that a lot of significant work has been done on the historic building.
The building served as the seat of the Liberian presidency for several decades before the Executive Mansion was constructed.
He said the facing and the exterior portions of the building have been completed. “The only major work that is holding us on the building now is the POP (the Plaster of Paris).
The POP is an ancient ceiling used by the rich during gothic period and is still one of the best in the world. It was reportedly discovered and widely used in Paris, France, thus the Plaster of Paris.
“We have to do the POP before we can do any other work. You have to do the POP before you can do wall paneling, tile laying and any other interior work,” Kemokai explained. Though it has been used since ancient days, the ACMC Project Manager indicated that the POP is new in Liberia and it takes more time and technicalities to install.
Though Minister Woods attributed the slow pace of work to his ministry and stated that he was not satisfied with progress, Mr. Kemokai said the Ministry of Public Works was fully cooperation and the work was progressing fine.
The work was expected to have been completed this month (July), but a new date will now be set after today’s meeting. D K Sengbeh writes, dakasen1978@yahoo.com, +231-6 586 531
AllAfrica – All the Time
Continued here:
Woods Takes Blame -for Slow Works On Executive Pavilion